Below is a list of current and upcoming paving work:
- Bruce Gordon P - complete
- Cultra Ave - complete
- West Saanich Rd between Verdier Ave and Stelly’s Cross Rd: Beginning Monday, October 23, through Wednesday, October 25
- Wallace Dr, south of Mt Newton Cross Rd to Cultra: Monday, November 6. No Parking signs will be posted in the North bound lane Sunday evening. Weather dependent.
- Stelly’s Cross Rd between West Saanich Rd and Gowdy Rd: Wednesday, October 25 to Friday, October 27
- Enid Pl: November (Dates to be determined)
In 2018, after all work on the Brentwood watermain upgrade is complete and after minor setting of the new watermain trenches, we will place a new and final layer of pavement over the affected areas to bring the roadway back to new condition.